July 13, 2016 – Formal Consultation meeting held at the City of Hamilton.

November 17, 2017 – Formal Consultation Waiver issued by the City of Hamilton.

December 1, 2017 – Applications for Official Plan / Zoning By-law Amendment and Draft Plan of Subdivision submitted to the City of Hamilton.

December 20, 2017 – Applications for Official Plan / Zoning By-law Amendment and Draft Plan of Subdivision deemed complete by the City of Hamilton.

January 4, 2017 – Notice of Circulation to the public.

May 25, 2018 – Planning Justification Report Addendum; revised Draft Plan of Subdivision; revised Concept and Parking Plan; revised Functional Servicing Report and Stormwater Management Report; revised Engineering package including Grading & Erosion Control Plan, Servicing Plan, Storm Drainage Area Plan, and Sanitary Drainage Area Plan; and revised Noise Impact Study submitted to the City of Hamilton.